29 October 2025 · Question time · Housing
Housing
Davis asked why apartment and house approval-to-completion times have risen. Shing cited Victoria's housing accord progress and Master Builders data, and Davis raised several points of order that the answer did not address the question.
What the 10 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
David Davis, Liberal
Davis cited Master Builders data showing apartment approval-to-completion rose from 21.54 to 28.56 months. He asked why the government has allowed a 32 per cent increase.
Harriet Shing, Labor
Shing said the question spans several portfolios and pointed to housing statement and planning reforms. She said Victoria is building more homes more quickly than other jurisdictions.
“We are building more homes more quickly and in more typologies than other jurisdictions, and that is not happening by accident.”
Harriet Shing, Labor
Shing said a Liberal frontbencher had acknowledged that Victoria has built more homes than other states.
Harriet Shing, Labor
Shing said Victoria is at 98 per cent of its housing accord target and is building more homes than the rest of Australia.
“Mr Davis, we are building more homes than the rest of Australia.”
Harriet Shing, Labor
Shing said the government is building more quality homes and that the Opposition opposed the buyer protection legislation.
Harriet Shing, Labor
Shing said Victoria meets 98 per cent of the Commonwealth accord target, in contrast to New South Wales and Queensland, and told Davis to stop blocking.
David Davis, Liberal
Davis said the minister refused to answer. He cited Master Builders figures showing house approval-to-completion rose from 8.28 months under the Baillieu government to 9.78 months, an 18 per cent increase, and asked why.
“Why has it gone up 18 per cent for houses?”
Harriet Shing, Labor
Shing quoted a Master Builders statement describing the latest data as good news for Victorian home builders.
David Davis, Liberal
Davis said the 2024-25 figure is still far higher than under the Baillieu government and asked why those figures cannot be achieved.
“Yes, and that figure is still far higher than it was under the Baillieu government.”
Harriet Shing, Labor
Shing cited 2024-25 Master Builders data: a Victorian detached house takes 39.12 weeks to build against the national 45.96 weeks. She said apartments took 32.9 months and told Davis to stop selective quoting.
“Mr Davis, stop selectively quoting and get on board with building.”
Other debates on this
- Housing · House of Representatives, 3 August 2022
- Housing · House of Representatives, 4 August 2022
- Housing · House of Representatives, 5 September 2022
- Housing · House of Representatives, 6 September 2022
- Housing · House of Representatives, 8 September 2022
- Housing · House of Representatives, 26 September 2022
- Housing · Senate, 26 September 2022
- Housing · Senate, 27 September 2022
- Housing · House of Representatives, 28 September 2022
- Housing · House of Representatives, 25 October 2022
- Housing · House of Representatives, 26 October 2022
- Housing · House of Representatives, 26 October 2022
Source: Parliament of Victoria Hansard, Parliament of Victoria. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.