19 February 2025 · Question time · Transport and infrastructure
Suburban Rail Loop
Mulholland asked Shing about contaminated sites in the Suburban Rail Loop East early works and how they will be handled. Shing spoke about early works, ground conditions and community engagement.
What the 6 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
Evan Mulholland, Liberal
Mulholland said the Auditor-General's report shows SRL East early works are in a pricing reset because of unknown ground conditions and contamination, and asked Shing to release a list of contaminated sites.
“Will you release a list of which sites are contaminated?”
Harriet Shing, Labor
Shing said Mulholland had not delivered major projects and would not understand how early works are undertaken.
“you would not understand the way in which early works are undertaken.”
Harriet Shing, Labor
Shing withdrew a remark and said tunnelling projects normally have variability in early works. She said the $300 million keeps the project in budget and that tunnel-boring machines will be in the ground next year.
“it is really normal to have a high degree of variability in those early works processes.”
Harriet Shing, Labor
Shing said tunnel-boring machines will be in the ground next year and trains running in 2035. She said SRL East received planning approval in September 2022 and early works help identify risks.
“Trains will be running on this 26-kilometre dual-tunnel project in 2035, unless of course you are saying that you are going to rip up this contract and these processes.”
Evan Mulholland, Liberal
Mulholland said problems have been exposed since the environment effects statement and asked how the minister and SRLA will deal with the contaminated sites.
“how will the minister and the SRLA deal with these contaminated sites?”
Harriet Shing, Labor
Shing said the condition of industrial land is not fully known before early works, and that SRLA will notify and engage with adjacent communities as part of normal processes.
“we will notify communities as part of normal engagement processes.”
Other debates on this
- Suburban Rail Loop · House of Representatives, 25 October 2022
- Suburban Rail Loop · House of Representatives, 28 November 2022
- Suburban Rail Loop · Victorian Legislative Council, 21 February 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 21 March 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 17 May 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 30 August 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 3 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 18 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 2 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 14 November 2023
- Suburban Rail Loop · Victorian Legislative Council, 15 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 8 February 2024
Source: Parliament of Victoria Hansard, Parliament of Victoria. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.