19 February 2025 · Question time · Transport and infrastructure · Integrity and democracy
Suburban Rail Loop
Davis asked the Treasurer why a $300 million Suburban Rail Loop early works increase in the Auditor-General's report was not disclosed in the budget. Symes said it was an approved amount not in the budget papers and the project is on time and on budget. Davis moved to take note of the answer.
What the 6 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
David Davis, Liberal
Davis asked why a $300 million blowout to the Suburban Rail Loop early works package, in the Auditor-General's report, was not disclosed in the budget.
“why was this blowout not disclosed, and instead hidden from the public?”
Jaclyn Symes, Labor
Symes said the report covers total estimated investment changes already disclosed in last year's budget, and that increases can reflect scope changes or Commonwealth contributions. She gave a car parks example.
“An increase in TEI simply means more investment in a project very often, and this can be attributed to a range of factors.”
Jaclyn Symes, Labor
Symes confirmed the $300 million is an amount approved by government to plan and develop the Suburban Rail Loop which is not included in the budget papers.
“what I can confirm, Mr Davis, is that the $300 million refers to an amount approved by government to plan and develop SRL which is not included in the budget papers.”
David Davis, Liberal
Davis said the report states the amount was not specifically disclosed in budget papers, noted a 'pricing reset' on SRL East early works, and asked whether future blowouts would be made public in the budget.
“Will you depart from your predecessor and make any additional blowouts public in the budget rather than hiding them?”
Jaclyn Symes, Labor
Symes said the project remains on time and on budget in relation to commitments given.
“this project remains on time and on budget in relation to the commitments that have been given.”
Jaclyn Symes, Labor
Symes said tunnel-boring machines will be in the ground and trains running by 2035, that the project will cost money and is worth it, and said she would back it against an opposition she described as criticising everything.
“we will have tunnel-boring machines in the ground; we will have trains running on those lines by 2035.”
Other debates on this
- Suburban Rail Loop · House of Representatives, 25 October 2022
- Suburban Rail Loop · House of Representatives, 28 November 2022
- Suburban Rail Loop · Victorian Legislative Council, 21 February 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 21 March 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 17 May 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 30 August 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 3 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 18 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 2 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 14 November 2023
- Suburban Rail Loop · Victorian Legislative Council, 15 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 8 February 2024
Source: Parliament of Victoria Hansard, Parliament of Victoria. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.