Davis asked Shing why the government resisted releasing the Suburban Rail Loop risk register and whether funding risk has grown. Shing said the register is part of an ongoing risk process under the Financial Management Act and pointed to the 2021 business case and $2.2 billion in the federal budget.
What the 8 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
David Davis, Liberal
Davis asked why the government fought for three years to stop release of the SRL risk register, and whether this was to avoid embarrassment.
“Minister, why did the government fight for three years to prevent the release of the SRL risk register?”
Harriet Shing, Labor
Shing said Davis's reference to 'the risk register' showed a lack of understanding of the integrated management framework under the Financial Management Act.
“When you say ‘the risk register’, what you are doing there is betraying your lack of understanding about what it means to have an integrated strategy and financial management framework.”
Harriet Shing, Labor
Shing said the business case released 19 August 2021 gives a benefit-cost ratio of 1.1 to 1.7, and described risk reporting as an ongoing process rather than a single register. She compared it with the east-west link business case.
“It is not ‘the risk register’, it is an ongoing process of being able to report the costs and benefits aligned with the delivery of a major project, Mr Davis.”
David Davis, Liberal
Davis raised a point of order that his question was narrow, about one project, and that the minister should answer it.
“It is a narrow question about one project.”
Harriet Shing, Labor
Shing said the interjections showed Davis was defensive, and offered to table the business case document.
Harriet Shing, Labor
Shing said the Financial Management Act requires public sector agencies including the SRLA to have a risk management framework, and asked whether Davis had such frameworks for his own office.
“The Financial Management Act creates obligations under any public sector agency – that includes the SRLA – to have a risk management framework.”
David Davis, Liberal
Davis said the minister did not answer on the delay and asked whether risk is now greater, given the 2020 register flagged funding in red and the Commonwealth has added no funding.
“Minister, isn’t it a fact that the risk is now even greater, given that almost five years have elapsed and that the Commonwealth still refuses to add any additional funding?”
Harriet Shing, Labor
Shing pointed to page 65 of the annual report on risks and contingencies, rejected the premise of 'the' register, cited $2.2 billion in the federal budget, and asked whether Dutton would scrap the project.
“Mr Davis, there is $2.2 billion in the federal budget.”
Other debates on this
- Suburban Rail Loop · House of Representatives, 25 October 2022
- Suburban Rail Loop · House of Representatives, 28 November 2022
- Suburban Rail Loop · Victorian Legislative Council, 21 February 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 21 March 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 17 May 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 30 August 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 3 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 18 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 2 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 14 November 2023
- Suburban Rail Loop · Victorian Legislative Council, 15 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 8 February 2024
Source: Parliament of Victoria Hansard, Parliament of Victoria. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.