12 November 2024 · Question time · Transport and infrastructure · Economy and tax
Suburban Rail Loop
Southwick asked Pearson about Suburban Rail Loop funding and contracts signed before the project proposal report went to the Commonwealth, and when money would be needed. Pearson said the report had been provided and described the project's funding split and timeline.
What the 11 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
David Southwick, Liberal
Southwick asked why the government signed multibillion-dollar contracts before providing the required project proposal report to the Commonwealth, citing Catherine King on $2.2 billion for Suburban Rail Loop East.
“Why did the Allan Labor government sign multibillion-dollar contracts –”
David Southwick, Liberal
Southwick repeated his question about contracts signed without the project proposal report being given to the Commonwealth.
“Why did the Allan Labor government sign multibillion-dollar contracts without first providing the required project proposal report to the Commonwealth?”
Danny Pearson, Labor
Pearson said the question's basis was wrong and the report was provided recently. He said Terra Verde was selected to build the twin tunnels between Glen Waverley and Box Hill.
“The basis of the member’s question is wrong. The PPR was provided to the Commonwealth recently, and I am really pleased that we can now get on and deliver this project”
Danny Pearson, Labor
Pearson said the report had been provided and the Terra Verde contract signed. He cited 70,000 additional homes along the corridor and said the project was endorsed at two elections.
“That is why we are committing to 70,000 additional homes right along the corridor.”
Danny Pearson, Labor
Pearson said the government was getting on with delivering the project.
“We are getting on and we are not wasting a day.”
John Pesutto, Liberal
Pesutto raised a point of order on relevance, saying the minister had signed contracts before information went to the Commonwealth and asking that he be drawn back to the question.
“The question asked why he signed contracts before providing the material to the Commonwealth.”
Danny Pearson, Labor
Pearson said the Commonwealth's $2.2 billion reflected that the project stacks up, and that the government would keep delivering it.
“This project stacks up and makes sense.”
David Southwick, Liberal
Southwick quoted the minister saying the money did not need to be in the next budget 'or else we're cooked' and asked by what date the money was needed.
“By what date is the money needed before the state’s finances are cooked?”
Danny Pearson, Labor
Pearson said the project would cost $30 billion to $34.5 billion, funded in thirds by the state, value capture and the Commonwealth. He said it was a multi-decade project with many budgets.
“The project will cost between $30 billion and $34.5 billion. One-third of the funding will be provided by the state, one-third through value capture and one-third through contributions from the Commonwealth.”
Danny Pearson, Labor
Pearson said the government would work with the Commonwealth, that there would be many budgets, and that the opposition had not started or finished a major project.
“There will be plenty of budgets; there will be plenty of opportunities.”
Danny Pearson, Labor
Pearson said the project would be funded by state contribution, value capture and Commonwealth contribution, and delivered by 2035.
“We said the project will be delivered by 2035. We are on track to deliver just that.”
Other debates on this
- Suburban Rail Loop · House of Representatives, 25 October 2022
- Suburban Rail Loop · House of Representatives, 28 November 2022
- Suburban Rail Loop · Victorian Legislative Council, 21 February 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 21 March 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 17 May 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 30 August 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 3 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 18 October 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 2 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 14 November 2023
- Suburban Rail Loop · Victorian Legislative Council, 15 November 2023
- Suburban Rail Loop · Victorian Legislative Assembly, 8 February 2024
Source: Parliament of Victoria Hansard, Parliament of Victoria. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.