28 August 2024 · Question time · Transport and infrastructure · Health
Metro Tunnel
Pesutto asked the Premier about electromagnetic interference from the Metro Tunnel affecting MRIs at Peter MacCallum Cancer Centre and about $888 million in project disputes. Allan said patient care had not been affected.
What the 8 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
John Pesutto, Liberal
Pesutto asked why cancer patients at Peter MacCallum should suffer disruption from Metro Tunnel interference requiring transfers for MRIs.
“Why should these cancer patients suffer pain and disruption to their treatment because of Labor’s failure to manage the Metro Tunnel project?”
Jacinta Allan, Labor
Allan said the Metro Tunnel will bring heavy rail to Parkville and that there had been no impact on patient care during construction and testing.
“there has not been any impact on patient care during the period of construction, and now the testing phase, which we are in”
Jacinta Allan, Labor
Allan said test trains were running through the new tunnels and that the government had been determined to deliver the project.
“we are having test trains running tens of thousands of kilometres through the brand new 9-kilometre twin tunnels”
Jacinta Allan, Labor
Allan thanked Parkville hospitals, universities and institutes for working with the project, and said 15,000 kilometres of train testing had been done.
“we have had something like 15,000 kilometres of train testing undertaken”
Jacinta Allan, Labor
Allan repeated there had been no impact on patient care and said extra support was provided to the Royal Melbourne and Royal Women's hospitals. She said the Opposition had abandoned the project.
“I repeat, as I said at the outset of my answer, that there has been no impact to patient care.”
John Pesutto, Liberal
Pesutto asked whether an additional $888 million on undisclosed Metro Tunnel disputes would ensure Peter Mac cancer patients can get MRI scans.
“Will this additional funding ensure that cancer patients can receive MRI scans at Peter Mac?”
Jacinta Allan, Labor
Allan said the government is focused on supporting patient care while delivering the project and working with construction partners.
“we are focused on supporting patient care while we get on and deliver the Metro Tunnel project.”
Jacinta Allan, Labor
Allan said the government will keep working with construction partners and that the project will be delivered a full year ahead of schedule.
“a project that will be delivered a full year ahead of schedule.”
Other debates on this
- Metro Tunnel · Victorian Legislative Assembly, 8 March 2023
- Metro Tunnel · Victorian Legislative Assembly, 30 August 2023
- Metro Tunnel · Victorian Legislative Council, 28 May 2024
- Metro Tunnel · Victorian Legislative Assembly, 20 June 2024
- Metro Tunnel · Victorian Legislative Council, 20 June 2024
- Metro Tunnel · Victorian Legislative Assembly, 27 August 2024
- Metro Tunnel · Victorian Legislative Assembly, 27 August 2024
- Metro Tunnel · Victorian Legislative Council, 27 August 2024
- Metro Tunnel · Victorian Legislative Assembly, 16 October 2024
- Metro Tunnel · Victorian Legislative Assembly, 17 October 2024
- Metro Tunnel · Victorian Legislative Council, 28 November 2024
- Metro Tunnel · Victorian Legislative Council, 4 February 2025
Source: Parliament of Victoria Hansard, Parliament of Victoria. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.