7 March 2024 · Question time · Transport and infrastructure
Western suburbs rail lines
Pesutto asked when construction would start on rail duplication and electrification to Melton and Wyndham Vale. Pearson cited level crossing removals on the Melton and Werribee lines. Multiple relevance points of order were raised.
What the 15 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
John Pesutto, Liberal
Pesutto asked when construction will start on duplicating and electrifying the Melton and Wyndham Vale lines, promised at the last two elections.
“Six years on, when will construction start?”
Danny Pearson, Labor
Pearson said the government is removing four level crossings on the Melton line, a $650 million investment, and will make the Werribee line level crossing free.
“That is a $650 million investment.”
John Pesutto, Liberal
Pesutto raised a point of order that the question was short and asked when construction would start.
Danny Pearson, Labor
Pearson said the opposition never built or delivered anything.
James Newbury, Liberal
Newbury cited standing order 58 and said ministers were not responding to questions.
Danny Pearson, Labor
Pearson repeated the level crossing investments on the Melton and Werribee lines and said the opposition delivered no major project in government.
James Newbury, Liberal
Newbury said standing order 58 requires succinct answers and the minister was not answering.
Danny Pearson, Labor
Pearson said a track cannot be electrified without removing level crossings and duplicating it.
“You cannot electrify a track unless you remove level crossings. You cannot electrify a track unless you duplicate it.”
Danny Pearson, Labor
Pearson made remarks about the opposition's week.
James Newbury, Liberal
Newbury said the minister was debating the question.
Danny Pearson, Labor
Pearson repeated that level crossings must be removed and track duplicated before electrification, and offered the opposition a briefing on the regional rail plan.
“You have got to remove level crossings before you can electrify. You have got to duplicate before you can electrify.”
John Pesutto, Liberal
Pesutto asked whether Labor cannot afford to deliver the promised Melton and Wyndham Vale upgrades.
“Is it the case that Labor cannot afford to deliver the promised upgrades to the Melton and Wyndham Vale lines?”
Danny Pearson, Labor
Pearson said the Leader of the Opposition had no plan B and had not listened to the earlier answer.
John Pesutto, Liberal
Pesutto raised a point of order that the supplementary question differed from the first.
Danny Pearson, Labor
Pearson said the government is investing in road and rail across the western suburbs and the Werribee and Melton lines will be level crossing free.
“We are making sure the Werribee line will be level crossing free. The Melton line will be level crossing free.”
Other debates on this
- Western suburbs rail lines · Victorian Legislative Assembly, 2 August 2023
- Western suburbs rail lines · Victorian Legislative Assembly, 2 August 2023
- Western suburbs rail lines · Victorian Legislative Assembly, 10 September 2026
Source: Parliament of Victoria Hansard, Parliament of Victoria. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.