10 May 2023 · Committee report · Defence and foreign affairs
Report No. 21 of 2022-23: Consideration
Shoebridge moved to take note of Auditor-General Report No. 21 of 2022-23 on Defence procurement of Hunter class frigates, arguing there was no value-for-money check before a $45 billion contract was signed. Debate was adjourned.
What was said
Summarised by AI from the official record. Quotes are checked word for word against it.
David Shoebridge, Greens
Shoebridge said the audit found no value-for-money assessment was done on Hunter class frigates before contracting, that the project is 18 months delayed and half a billion dollars over budget, and that there have been 95 contract variations.
“Has it delivered value for money? Absolutely not.”