18 September 2025 · Question time · Transport and infrastructure
Wakehurst Parkway Flooding
Scruby asked when flood mitigation works on Wakehurst Parkway would start. Aitchison gave a timeline of a tender then a contract in early 2026.
What the 5 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
Jacqui Scruby, Independent
Scruby asked when construction would start on flood mitigation works on Wakehurst Parkway.
“It closed 22 times in 2022 and has closed as recently as last week.”
Jenny Aitchison, Labor
Aitchison said the Government committed $13 million to flood mitigation, a tender is expected in coming weeks, a contract is expected in early 2026, and the former Liberal Government decided in 2013 the work was too hard and too expensive.
“That is why we made an election commitment of an additional $13 million for flood mitigation works on Wakehurst Parkway.”
Jenny Aitchison, Labor
Aitchison said $31.1 million is committed, with $24 million to be worked through with Northern Beaches Council and $7.1 million for the first site, and said the former Government neglected local roads in electorates it considered safe.
“There is $31.1 million in funding, of which $24 million is being worked through with Northern Beaches Council, and the remaining $7.1 million will go towards that work at site one.”
Alister Henskens, Liberal
Henskens interjected asking why the Minister did not just fix the road.
Jenny Aitchison, Labor
Aitchison said the Government is fixing the road, that the Opposition did not do it in government, and that construction will start in 2026.
“We are fixing the road.”
Source: Parliament of Australia Hansard, Parliament of New South Wales. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.