30 October 2025 · Motion · Transport and infrastructure
Public Works Joint Committee: Approval of Work
Leigh moved that it is expedient to carry out the fit-out of leased premises at 7 London Circuit, Canberra City, estimated at $23.4 million. The question was agreed to.
What was said
Summarised by AI from the official record. Quotes are checked word for word against it.
Andrew Leigh, Labor
Leigh said the department proposes a $23.4 million fit-out of leased office space at 7 London Circuit, with works to finish in May 2026 and staff relocating April to June 2026.
“The estimated cost of the fit-out works is $23.4 million, excluding GST.”
Other debates on this
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Report · House of Representatives, 6 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Report · House of Representatives, 26 October 2022
- Public Works Joint Committee: Reference · Senate, 26 October 2022
- Public Works Joint Committee: Approval of Work · House of Representatives, 9 November 2022
- Public Works Joint Committee: Reference · Senate, 24 November 2022
- Public Works Joint Committee: Report · House of Representatives, 28 November 2022
Source: Parliament of Australia Hansard, Parliament of Australia. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.