Members debated the interim report of the Nuclear Energy Select Committee on nuclear power generation in Australia. Government members argued the report found nuclear too slow, costly and risky, while coalition members disputed its conclusions and cited cost estimates, water use and the energy mix.
What the 9 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
Matt Burnell, Labor
Burnell thanked the committee chair, secretariat and power station hosts, and argued that social licence, cost blowouts and timing make nuclear unfeasible. He cited Hinkley Point C, Vogtle and small modular reactor availability.
“This enquiry has found that it is not feasible to pursue nuclear power generation in Australia.”
Colin Boyce, Nationals
Boyce supported nuclear power, citing Central Queensland forums and a proposal at Callide. He argued that industry in Flynn needs reliable baseload power and questioned renewable cost estimates, including the Lotus Creek wind farm and the Capacity Investment Scheme.
“Nuclear energy, as I said, is widely accepted where I come from.”
Zaneta Mascarenhas, Labor
Mascarenhas argued that nuclear is too slow, too expensive and incompatible with the grid, and that renewables and firming offer a better path. She referred to a visit to Collie and the closure of a coal-fired power station in Western Australia.
“Nuclear is the most expensive form of electricity.”
Rowan Ramsey, Liberal
Ramsey opposed the report, arguing that South Australian electricity prices and renewable firming costs show the need for nuclear. He described the Port Augusta power station closure, the Kimba waste facility and a flyer sent to Port Augusta residents.
“The world is choosing nuclear in the mix.”
Graham Perrett, Labor
Perrett opposed nuclear at Callide and Tarong on water grounds, citing dam levels, drought declarations and water use. He quoted the Queensland Conservation Council and listed renewable projects approved by the government.
“There simply is not enough water available in the proposed locations to run nuclear facilities, and no plan for where to store irradiated water required for heat reduction in the case of an emergency.”
Rick Wilson, Liberal
Wilson argued that the coalition's nuclear plan has a lower total system cost than the renewables-only plan, citing Frontier Economics figures. He spoke about Collie as a proposed small modular reactor site, WA power costs and the Sandy Ridge storage site.
“In comparison, the total system cost of the coalition's plan to transform the entire National Electricity Market through to 2050, including nuclear energy, is $331 billion.”
Jerome Laxale, Labor
Laxale argued that nuclear is too slow, too expensive and too risky, citing the GenCost report and overseas delays. He said Coalition nuclear policy would extend coal plants and listed renewable projects, batteries and the Capacity Investment Scheme.
“Nuclear energy is too slow, it's too expensive and it's too risky.”
Elizabeth Watson-Brown, Greens
Watson-Brown argued that nuclear is the most expensive option and would arrive too late, citing delays and cost overruns at Flamanville 3, Hinkley Point C and Vogtle. She said reactors are vulnerable to water shortages and jellyfish, and that the coalition plan relies on coal and gas.
“Nuclear—when do we get it? The short answer is never.”
David Gillespie, Nationals
Gillespie disputed the report, arguing that coal still supplies much of eastern Australia's power and that renewables have low capacity factors. He said firming and network costs drive bills, and that modern small reactors can ramp output.
“Capacity factor is how often an installed capacity actually generates.”
Other debates on this
- Nuclear Energy Select Committee: Appointment · House of Representatives, 10 October 2024
- Nuclear Energy Select Committee: Membership · House of Representatives, 10 October 2024
- Nuclear Energy Select Committee: Membership · House of Representatives, 4 November 2024
- Nuclear Energy Select Committee: Membership · House of Representatives, 4 November 2024
- Nuclear Energy Select Committee: Membership · House of Representatives, 7 November 2024
- Nuclear Energy Select Committee: Membership · House of Representatives, 18 November 2024
- Nuclear Energy Select Committee: Report · House of Representatives, 26 March 2025
- Nuclear Energy Select Committee: Report · House of Representatives, 26 March 2025
Source: Parliament of Australia Hansard, Parliament of Australia. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.