22 August 2024 · Committee report · Defence and foreign affairs · Transport and infrastructure
Public Works Joint Committee: Approval of Work
Leigh moved three motions that it is expedient to carry out public works: Submarine Rotational Force-West at HMAS Stirling ($738.1 million), fit-out of Commonwealth parliament offices at One Festival Tower in Adelaide ($37.45 million), and the Reserve Bank head office storage and logistics change ($35.3 million). Each question was agreed to.
What was said
Summarised by AI from the official record. Quotes are checked word for word against it.
Andrew Leigh, Labor
Leigh moved the three public works motions and summarised each project's scope, cost and timing. He thanked the committee, chaired by the member for Moreton, and commended the motions to the House.
“The cost of the project elements is $738.1 million, excluding GST.”
Other debates on this
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Report · House of Representatives, 6 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Report · House of Representatives, 26 October 2022
- Public Works Joint Committee: Reference · Senate, 26 October 2022
- Public Works Joint Committee: Approval of Work · House of Representatives, 9 November 2022
- Public Works Joint Committee: Reference · Senate, 24 November 2022
- Public Works Joint Committee: Report · House of Representatives, 28 November 2022
Source: Parliament of Australia Hansard, Parliament of Australia. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.