Public Works Joint Committee: Reference
Leigh moved a motion to refer the Department of Defence's Submarine Rotational Force—West priority works at HMAS Stirling, Perth, to the Parliamentary Standing Committee on Public Works. The estimated cost is $738.1 million excluding GST. The question was agreed to.
What was said
Summarised by AI from the official record. Quotes are checked word for word against it.
Andrew Leigh, Labor
Leigh moved the referral and described the scope of works at HMAS Stirling, including dredging, pier and power upgrades and a pure water plant. He said works are expected to start in early 2025 and finish in early 2027.
“The estimated project cost is $738.1 million, excluding GST.”
Other debates on this
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Report · House of Representatives, 6 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Report · House of Representatives, 26 October 2022
- Public Works Joint Committee: Reference · Senate, 26 October 2022
- Public Works Joint Committee: Approval of Work · House of Representatives, 9 November 2022
- Public Works Joint Committee: Reference · Senate, 24 November 2022
- Public Works Joint Committee: Report · House of Representatives, 28 November 2022
Source: Parliament of Australia Hansard, Parliament of Australia. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.