28 November 2023 · Committee report · Defence and foreign affairs · Energy
Public Works Joint Committee: Report
Perrett presented the Public Works Committee report on the Defence fuel transformation program tranche 2, at a total cost of $286.9 million across nine sites. The committee recommended that the works proceed.
What was said
Summarised by AI from the official record. Quotes are checked word for word against it.
Graham Perrett, Labor
Perrett presented the committee report, describing works to replace ageing fuel storage at nine Defence sites, the $286.9 million cost and the savings to be redirected to the third tranche. He said the committee recommends the work proceed.
“The committee recommends that it is expedient that the proposed work be carried out, and I commend the report to the House.”
Other debates on this
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Reference · Senate, 3 August 2022
- Public Works Joint Committee: Report · House of Representatives, 6 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Reference · Senate, 27 September 2022
- Public Works Joint Committee: Report · House of Representatives, 26 October 2022
- Public Works Joint Committee: Reference · Senate, 26 October 2022
- Public Works Joint Committee: Approval of Work · House of Representatives, 9 November 2022
- Public Works Joint Committee: Reference · Senate, 24 November 2022
- Public Works Joint Committee: Report · House of Representatives, 28 November 2022
Source: Parliament of Australia Hansard, Parliament of Australia. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.