16 October 2023 · Motion · Transport and infrastructure
Infrastructure
Pasin moved a motion noting the 90-day Infrastructure Investment Pipeline review had run over 130 days, and calling on the government to finish it and release the outcomes. Six members spoke on delayed projects in their electorates.
What the 7 speakers said
Summarised by AI from the official record. Quotes are checked word for word against it.
Tony Pasin, Liberal
Pasin said the review is delaying projects including the Truro freight route in Barker, plus Roads to Recovery and Black Spot funding. He called on the government to release the completed review.
“We know the review has been completed. The document is sitting on the minister's desk.”
Dan Repacholi, Labor
Repacholi cited Singleton and Muswellbrook bypass progress and a $38.6 million commitment to fix Coulson's Creek Road. He said the government will keep the $120 billion pipeline.
“As a government, we are committed to maintaining the 10-year infrastructure pipeline at $120 billion, and we will ensure that the transport infrastructure projects that we deliver are nationally significant and nation-shaping projects.”
Jason Wood, Liberal
Wood said the review has blown out to 169 days and listed La Trobe projects including Clyde Road, Racecourse Road and McGregor Road. He said the state Labor government supported these projects.
“I rise to support this motion on investment in infrastructure and am greatly concerned about this 90-day review, which has now blown out to 169 days and counting.”
Josh Burns, Labor
Burns said the independent review shows mismanagement by the former government. He cited the Balaclava Station commuter car park funding and said the minister will respond to the review's recommendations.
“We're obviously taking this matter more seriously, and the minister is reviewing the report and will announce the government's formal response to the recommendations in due course.”
Mark Coulton, Nationals
Coulton supported the motion and said the review is delaying Inland Rail work and regional roads. He cited Moree grade separations, the Coonamble-to-Tooraweenah road and the Gilgandra bypass.
“So I wholly support member for Barker on this motion.”
Michael McCormack, Nationals
McCormack agreed with the motion, saying regional projects have stalled during the 169-day review. He cited Inland Rail, potholes in regional areas and the cancelled Commonwealth Games contract.
“The projects put in place by the former government were good projects.”
Aaron Violi, Liberal
Violi backed the motion and described delayed upgrades at Killara Road in Coldstream and Canterbury Road in Montrose. He said the Suburban Rail Loop received funding while regional road upgrades were paused.
“This is a dangerous road, a dangerous intersection that needs lights.”
Other debates on this
- Infrastructure · House of Representatives, 27 September 2022
- Infrastructure · Senate, 28 September 2022
- Infrastructure · Senate, 28 September 2022
- Infrastructure · Senate, 26 October 2022
- Infrastructure · Senate, 22 November 2022
- Infrastructure: Order for the Production of Documents · Senate, 29 November 2022
- Infrastructure · House of Representatives, 1 December 2022
- Infrastructure · House of Representatives, 7 March 2023
- Infrastructure · House of Representatives, 23 March 2023
- Infrastructure · Senate, 24 March 2023
- Infrastructure · House of Representatives, 27 March 2023
- Infrastructure · House of Representatives, 28 March 2023
Source: Parliament of Australia Hansard, Parliament of Australia. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.