Mallee Electorate: Energy
Anne Webster criticised the VNI West transmission project and a VEPC report proposing an alternative plan B. She argued the project would raise costs for Victorian consumers and that the Mallee electorate is affected.
What was said
Summarised by AI from the official record. Quotes are checked word for word against it.
Anne Webster, Nationals
Webster said a Victoria Energy Policy Centre report proposes an alternative plan B for the VNI West transmission line that would cost less. She argued that the project's costs will be passed on to consumers and raised questions about CSIRO GenCost data.
“The difference in annual electricity bill costs between the VEPC's plan B and the extended VNI West is a whopping $940 million by 2036.”
Other debates on this
- Mallee Electorate: Energy · House of Representatives, 24 May 2023
- Mallee Electorate: Energy · House of Representatives, 13 June 2023
- Mallee Electorate: Energy · House of Representatives, 19 March 2024
- Mallee Electorate: Energy · House of Representatives, 26 November 2025
Source: Parliament of Australia Hansard, Parliament of Australia. Summaries and stances are written by AI (Claude) from the record and can be wrong; the record is the authority. We quote at most a sentence or two and link to the full text.